Case study

How HBC stopped paying for work that wasn't done

Their quantity surveyor checked subcontractor claims against 360° photos of the site. Room by room, on every visit. Here's what the photos showed.

£100k - £150k
identified in overclaimed works
££ Tens of thousands
avoided in potential disruption claims
Reduced
investigation time
HBC
United Kingdom · Yorkshire, Teesside & the East Midlands
Oculo timeline comparison of a corridor wall, stripped plaster in July 2025 beside the same wall finished in March 2026
16 Jul 2025 to 5 Mar 2026The same room, two scans apart. Every position on site is recorded on every visit.
Trusted by leading contractors worldwide
What we did for HBC

Delivering measurable savings through complete visual records of construction

The brief

Construction projects often require teams to answer questions long after work has been completed. Traditionally, this relied on site diaries and individual photographs.

What we deployed

HBC implemented Oculo across multiple projects, capturing regular 360° walkthroughs throughout construction.

✓Ramsden Building for the University of Huddersfield
✓Rotherham Markets
✓Rye Park in Newcastle-under-Lyme
The outcome
✓£100,000 - £150,000 identified in overclaimed works
✓Tens of thousands of pounds protected through subcontractor claim evidence
✓Pre-existing defects proven instantly using historical scans

Creating a Complete Visual Record

HBC implemented Oculo across multiple projects, capturing regular 360° walkthroughs throughout construction.

The scans created a permanent visual timeline, giving both commercial and site teams the ability to return to any location at any point in time. Whether reviewing completed works, investigating issues or validating commercial claims, teams can instantly access a visual record of exactly what happened on site.

Commercial Impact: £100,000 - £150,000 Identified in Overclaimed Works

One of Oculo's biggest commercial impacts came during the refurbishment of the Ramsden Building at the University of Huddersfield.

Senior Quantity Surveyor Ashley Etherington used Oculo during monthly valuations to verify subcontractor claims. Rather than relying solely on submitted quantities, Ashley reviewed completed works using Oculo's historical timeline.

In several cases, subcontractors had overclaimed on their works, while Oculo showed what had actually been completed. With traditional finishes in historic buildings coming at a premium, these discrepancies quickly became significant.

By validating completed works against Oculo's visual record, HBC estimates it identified approximately £100,000 - £150,000 in overclaimed works.

Oculo split-screen timeline showing the same room stripped out in May 2025 and with finishes in progress in February 2026
7 May 2025 to 17 Feb 2026Finishes verified against what was actually on site, not what was claimed for.

Resolving Contractor Disputes: Tens of Thousands of Pounds Protected

Oculo also became a key evidencing tool during conversations with subcontractors.

During a conversation, another subcontractor argued that delayed access had prevented works from starting on time. Using Oculo's timestamped imagery, HBC was able to demonstrate exactly when operatives were present on each floor.

“Our site management used Oculo to basically say, 'Here's a picture of some of your team on Floor 1 or Floor 2 at this date.'”

Ashley Etherington · Senior Quantity Surveyor, HBC

Ashley estimates this evidence helped avoid tens of thousands of pounds in potential disruption claims.

Protecting Against Existing Defects

For Site Manager Carl Gelder, one of Oculo's biggest benefits came during an investigation into hairline cracking on an existing building. Questions arose about whether the works had caused the damage.

Instead of searching through hundreds of photographs, Carl simply returned to the project's first Oculo scan. The scan clearly showed the cracking already existed before construction began.

“I could go straight back to our first scan and showed it was existing... without the system I would have been a bit stuck.”

Carl Gelder · Site Manager, HBC

The ability to prove pre-existing conditions protected the project from unnecessary remediation costs and lengthy investigations.

Oculo 360 scan from 13 June 2025 panning up to hairline cracking across the ceiling of the existing building
13 Jun 2025Hairline cracking on the existing building, on record in the Oculo timeline.

A Tool for the Entire Project Team

One of the biggest advantages highlighted by HBC was that Oculo delivers value across multiple roles throughout the project lifecycle.

Commercial Teams
✓Validate subcontractor payment applications
✓Challenge overclaimed works
✓Resolve commercial disputes
✓Support monthly valuations
Site Teams
✓Investigate existing conditions
✓Verify progress
✓Review historic site conditions
✓Support client discussions
✓Reduce investigation time

As Carl summarised: “It's a very rounded system.”

Results

Commercial savings
£100,000 - £150,000 identified in overclaimed works
Dispute resolution
Tens of thousands of pounds protected through subcontractor claim evidence
Existing condition verification
Pre-existing defects proven instantly using historical scans
Investigation time
Reduced from searching through photographs to instant visual verification
Commercial management
Stronger evidence for valuations and payment applications
Site management
Complete visual history supporting progress reviews and issue investigations
Future adoption
HBC plans to continue deploying Oculo on future projects

About HBC

HBC is one of the UK's leading construction companies, delivering complex construction projects across the public and private sectors in Yorkshire, Teesside and the East Midlands.

Across projects including the Ramsden Building for the University of Huddersfield, Rotherham Markets and Rye Park in Newcastle-under-Lyme, HBC adopted Oculo to create a complete visual record of construction.

Today, Oculo supports both commercial and site teams by providing instant access to historic site conditions, helping verify completed works, investigate issues and reduce project risk.

What would a complete record have caught on your last project?

Book a demo on one of your own sites. We'll walk the timeline, open a valuation and pull the evidence, the same way HBC's teams do every month.